摘要
传统的输电线路施工管理方法因技术时间计算不准确而导致施工关键环节无法明确,从而影响整体施工时间。基于不停电跨越技术,推出了一种创新的10kV电力工程输电线路施工管理方法。此方法首先根据各施工区域之间的关联性,进行施工管理流程的细化。然后使用不停电跨越技术来精确计算施工技术时间,进而明确施工的关键链路。对确定的关键施工环节进行深入分析后,评估并解决施工过程中的问题,从而确保施工管理流程的顺畅进行。基于不停电跨越技术的施工管理方法在实际中的应用证明,其能够有效提升施工管理效果,显著缩短工程施工时间。
The traditional construction management method for transmission lines is unable to accurately calculate the technical time,resulting in unclear key construction links and affecting the overall construction time.An innovative construction management method for 10kV power engineering transmission lines has been introduced based on uninterrupted crossing technology.This method first refines the construction management process based on the correlation between different construction areas.Then,the uninterrupted crossing technology is used to accurately calculate the construction technology time and clarify the key links of construction.After conducting in-depth analysis of the identified key construction processes,evaluate and solve problems during the construction process to ensure the smooth progress of the construction management process.The application of the construction management method based on uninterrupted crossing technology in practice has proven that it can effectively improve the effectiveness of construction management and significantly shorten the construction time.
作者
杨焕志
石军
Yang Huanzhi;Shi Jun(Shandong Jiruida Electric Appliance Installation Co.,Ltd.,Jinan,Shandong 250001)
出处
《现代工程科技》
2024年第5期121-124,共4页
Modern Engineering Technology
关键词
输电线路
电力工程
10kV
不停电跨越技术
transmission lines
electric power engineering
10kV
power outage crossing technology