盾构机长时间停机风险分析及规避研究

RISK ANALYSIS AND AVOIDANCE RESE ARCH ON LONG-TERM SHUTDOWN OF SHIELD TUNNELING MACHINES
下载PDF
导出
摘要 在盾构隧道施工过程中,由于各方面原因,盾构机可能出现长时间停机,而长时间停机容易造成盾构机沉陷、铰接油缸回缩困难、复推困难等问题。为规避这些风险,以某工程为例,通过分析停机风险,从停机准备工作、停机流程、停机期间工作等方面,总结正常掘进停机过程中的风险规避措施,并从机内措施、监控测量措施等方面介绍二次组装停机过程中的风险规避措施。实践表明,施工中各类措施行之有效,保证了工程项目顺利施工。 In the process of shield tunnel construction,due to various reasons,the shield machine may be shut down for a long time,and the long-term shutdown is easy to cause problems such as the subsidence of the shield machine,the difficulty of retracting the hinged cylinder,and the difficulty of repushing.In order to avoid these risks,taking a project as an example,by analyzing the shutdown risk,the risk avoidance measures in the normal tunneling shutdown process are summarized from the aspects of shutdown preparation,shutdown process,and work during shutdown,and the risk avoidance measures in the process of secondary assembly shutdown are introduced from the aspects of in-machine measures,monitoring and measurement measures,etc.Practice shows that various measures in the construction are effective to ensure the smooth construction of the project.
作者 梁长辉 Liang Chang-hui
出处 《建筑技术开发》 2024年第4期129-131,共3页 Building Technology Development
关键词 盾构隧道 盾构机 停机风险 shield tunnel shield machine stoppage risk
  • 相关文献

参考文献7

二级参考文献48

  • 1温竹茵,周质炎.盾构法隧道的纵向受力分析[J].特种结构,2002,19(2):14-16. 被引量:17
  • 2刘建海,孙明磊,杨治东.仑大区间盾构机海底脱困技术研究[J].铁道建筑,2006,46(5):39-41. 被引量:3
  • 3PECK R B. Deep excavations and tunneling in soft ground[C]//Proceedings of 7th International Conference on Soil Mechanics and Foundation Engineering. Mexico City: Thomas Telford, 1969: 225-290.
  • 4YOSHIKOSHI WATARU, WATANABE OSAMU, TAKAGI NOBUO. Prediction of ground settlements associated with shield tunnelling[J]. Soils and Foundations, 1978,18(4):47-59.
  • 5LEE K M, ROWE R KERRY, LO K Y. Subsidence owing to tunneling. I. Estimating the gap parameter[J]. Canadian Geotechnieal Journal, 1992, 29: 929- 940.
  • 6ROWE R KERRY, LEE K M. Subsidence owing to tunneling. II. Evaluation of a prediction technique[J]. Canadian Geoteehnieal Journal, 1992, 29:941 -954.
  • 7ROWE R KERRY, LEE K M. Subsidence owing to tunneling. II. Evaluation of a prediction technique: 1Reply[J]. Canadian Geotechnical Journal, 1994, 31: 467-469.
  • 8PARK K H. Elastic solution for tunnelling-induced ground movements in clays[J]. International Journal of Gemechanics, 2004, 4(4): 310- 318.
  • 9WEI-I CHOU, ANTONIO BOBET. Predictions of ground deformations in shallow tunnels in clay[J]. Tunnelling and Underground Space Technology, 2002, 17(1): 3- 19.
  • 10NOMOTO TOSHI, IMAMURA SHINICHIRO, HAGIWARA TOSHIYUKI, et al. Shield tunnelconstruction centrifuge[J]. Journal of Geotechnical and Geoenvironmental Engineering, 1999, 125(4): 289- 300.

共引文献54

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部