某核电站DCS从设计到调试的全流程创新案例分析

An Innovative Case Study of the Full Process of Design to Debugging in a Nuclear Power Plant DCS
下载PDF
导出
摘要 国内某核电站DCS在设计过程中对NC级信号分配提出了明确要求,避免了因信号通道分配不合理导致的跳机跳堆。在DCS装配测试过程中,在行业内首次应用最小化BUP盘参与测试,实现了DCS按期供货。在反应堆保护系统响应时间测量过程中创新设计了1套测试装置,将调试工期由3个月缩短为1个月。这些措施解决了行业内普遍存在的DCS设计、采购、调试的痛点。 During the design process of a domestic nuclear power plant's DCS(Distributed Control System),explicit requirements were set for the allocation of NC(Nuclear Class)signals,which avoided reactor trips due to unreasonable signal channel allocation.In the DCS assembly test process,the minimal BUP(Backup Processor)participation in testing was applied for the first time in the industry,achieving on-schedule DCS delivery.In the reactor protection system response time measurement process,an innovative set of testing equipment was designed,reducing the debugging period from three months to one month.These measures have resolved the widespread pain points in the DCS design,procurement,and debugging within the industry.
作者 张宝龙 Zhang Baolong(CNNP Suneng Nuclear Power Co.,Ltd.,Lianyungang Jiangsu 222000)
出处 《中国仪器仪表》 2024年第4期35-38,共4页 China Instrumentation
关键词 设计 装配 测试 调试 Design Assembly Testing Debugging
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部