深水J形首端PLET安装分析

J-Lay Installation Analysis of Head End PLET in Deepwater
下载PDF
导出
摘要 基于南海陵水17-2深水油气田开发,针对J形首端海底管道终端(Pipeline End Termination,PLET)安装,采用OrcaFlex软件开展数值模拟,研究波流载荷对安装系统的影响,以得到其作业窗口,并分析J形首端PLET安装过程中作业窗口的影响因素。结果表明,PLET在飞溅区和预着陆阶段比较危险,波浪周期约10 s波流同向横浪是安装作业的控制工况。研究内容为南海陵水17-2海底管道J形首端PLET安装提供了重要的技术支持。 Based on the development of Lingshui 17-2 deepwater oil and gas field in the South China Sea,the OrcaFlex software is used to carry out the numerical simulation for the installation of the head end Pipeline End Termination(PLET)by J-lay installation,the influence of wave and current loads on the installation system is studied to obtain its operating window,and the influence factors of the operating window during the installation process of J-lay head end PLET are analyzed.The results show that PLET is more dangerous in the splash zone and the pre-landing process,and the control condition of the installation operation is when the wave period is about 10 s and the wave and current are in the same direction as the transverse wave.The research provides important technical support for the installation of J-lay head end PLET in Lingshui 17-2 submarine pipeline in the South China Sea.
作者 王晓飞 李斌 李英 杨杰 WANG Xiaofei;LI Bin;LI Ying;YANG Jie(Installation Branch Company,Offshore Oil Engineering Co.,Ltd.,Tianjin 300461,China;School of Civil Engineering,Tianjin University,Tianjin 300461,China)
出处 《中国海洋平台》 2024年第2期82-88,共7页 China offshore Platform
基金 工信部“深水半潜式生产储卸油平台工程开发”(编号:SSBQ-2020-HN-04)。
关键词 J形铺设 海底管道终端 作业窗口 数值模拟 J-lay installation Pipeline End Termination(PLET) operability envelope numerical simulation
  • 相关文献

参考文献11

二级参考文献43

  • 1李清平.我国海洋深水油气开发面临的挑战[J].中国海上油气(工程),2006,18(2):130-133. 被引量:124
  • 2刘嵬辉,曾宝,程景彬,周云龙,刘长久.国内外铺管船概况[J].油气储运,2007,26(6):11-15. 被引量:48
  • 3Stephen j Rowe, Brain Maehenzie, Richard Snell. Deepwater installation of subsea hardware[C]///Proceedings of the lOth OffshoreSympositml. 2001.
  • 4F E Roved, L V S Sagrilo, E C P de Lima, et al. Comparing measured and calculated folrces of a manifold deployment in 940 meters water depth[C]//ASME 2003 22nd International Conference on Offshore Mechanics and Arctic Engineering. 2003:189-195.
  • 5F E Roveri, M C de Oliveira, M J Moretti. Installation of a production manifold in 2000 ft water depth offshore Brazil[C]//Offshore Technology Conference. 1996 : 10. 4043/8237-ms.
  • 6aPedro F K Stock, Maxwell B de Cerqueira, Francisco E Roveri. A new method for deploying subsea hardware in deep water[C] //Proceedings of the 2002 Deep OiIshore Teehnology. 2002,.
  • 7Jose Mauricio T G Lima, Mariele Lima Kuppens, Paulo Ferreira da Silveira, et al. Development of subsea facilities in the Roncador field[ C ]//Of/shore Technology Conference. 2008 : 10. 4043/19274-ms.
  • 8Pedro F k Stock, Mariele L Kuppens, Joao Luis b da Silva, et al. Roncador manifolds installation by the Pendulous method[C]//Preceedings of the 2007 Deep Offshore Technology. 2007.
  • 9F E Roveri, R D Machado, P F K Stock, et al. The unilization of the pendulous motion for deploying subsea hardware in ultra-deep water[ C]//Preceedings of the 2005 Deep Offshore Technology. 2005.
  • 10T Risoey, H Mork, H Johnsgard, et al. The pencil buoy method-a subsurface transportation and installation method[C]//Offshore Technology Conference. 2007.

共引文献59

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部