地铁工程投资巨大,社会资本采用PPP+EPC模式参与项目,承担投融资、设计、采购、施工、运营、维护等项目全生命周期工作,投资控制尤为重要。文章依托某PPP+EPC模式下的地铁项目,详细分析了项目结算与概算对比情况,从重大变更、材料调差、交通疏解、绿化补偿等费用问题着手,提出设计概算编制的完善建议,以期为今后PPP+EPC模式下的地铁项目投资控制提供借鉴。
The investment in subway engineering is huge,and social capital participates in the project through PPP+EPC mode,undertaking the full life cycle work of investment and financing,design,procurement,construction,operation,maintenance,and other projects.Among them,investment control is particularly important.The article relies on a subway project under the PPP+EPC mode to analyze in detail the comparison between project settlement and budget.Starting from major changes,material adjustments,traffic diversion,greening compensation and other cost issues,suggestions for improving the design budget preparation are proposed,in order to provide reference for investment control of subway projects under the PPP+EPC mode in the future.
作者
汪敏
WANG Min(China Railway Siyuan Group Southwest Survey and Design Co.,Ltd.,Kunming 650200,Yunnan,China)
出处
《工程技术研究》
2024年第3期146-148,共3页
Engineering and Technological Research