摘要
良好的通风设计是保证长大隧道施工安全的前提,需要做好隧道通风方案的设计和优化以及施工设备选择。依托棠棣岭隧道实际施工通风设计情况,介绍了工程概况和通风方案的确定;根据隧道施工中的通风特点计算出各工作面的所需风压和风量,并考虑了风管摩擦阻力作用和弯道处的风压损失;根据计算结果研究了隧道通风合理的设备选型以及相应的优化改进措施。结果表明:配置的压入式轴流风机和射流风机可以满足棠棣岭隧道施工通风的需要,合适的风机和风管选型可以达到需风量要求并有效降低风阻损失。
Well-designed ventilation is the premise to ensure the safety of long tunnel construction.It is necessary to design and optimize the ventilation scheme of tunnel and select construction equipment.Based on the actual construction ventilation design of Tangdiling Tunnel,this paper introduces the project overview and the determination of ventilation scheme.According to the ventilation characteristics of tunnel construction,the required air pressure and air volume of each working face are calculated,and the wind pressure loss under the action of duct friction resistance and the curve is considered.According to the calculation results,the reasonable equipment selection and corresponding optimization and improvement measures in tunnel ventilation construction are studied.The results show that the press-in axial fan and jet fan can meet the ventilation needs of Tangdiling Tunnel construction,and the suitable fan and duct selection can meet the requirements of air volume and effectively reduce the wind resistance loss.
作者
金鹏
刘感争
王卓君
包崇昊
杨雪
JIN Peng;LIU Ganzheng;WANG Zhuojun;BAO Chonghao;YANG Xue(CCCC Road and Bridge South Engineering Co.,Ltd.,Beijing 101101,China;College of Construction Engineering,Jilin University,Changchun,Jilin 130012,China)
出处
《黑龙江交通科技》
2024年第4期135-138,142,共5页
Communications Science and Technology Heilongjiang
基金
中交路桥建设有限公司科研项目。
关键词
长大隧道
施工通风
压入式通风
选型优化
long tunnel
construction ventilation
press-in ventilation
selection optimization