摘要 针对自升式钻井平台在插桩和拔桩过程中面临的土工问题,系统地梳理插桩和拔桩涉及的关键技术。分析插桩过程中的土工试验技术、土体破坏机理、上硬下软地层承载力和桩脚滑移问题;阐述拔桩过程中的拔桩阻力计算方法和减小拔桩阻力方法的研究进展情况。在此基础上,根据目前面临的新挑战,提出今后自升式钻井平台插拔桩技术研究的重点,并预测其发展趋势。 This paper systematically reviews the key technologies involved in the pile insertion and uplift for the geotechnical problems faced by jack-up drilling platforms.The geotechnical testing technology,soil failure mechanism,bearing capacity of upper hard and lower soft strata,and pile foot sliding issues met in the pile penetration process are analyzed.The research progress of calculation methods for pile pulling resistance and the methods for reducing pile pulling resistance during the pile uplift process are elaborated.On this basis,the focus of future research on the penetration and uplift technology of jack-up dilling platforms is proposed in accordance with the new challenges faced curently,and the developing trend is put forward.
作者 谭瑞龙 段梦兰 徐斌 陈栎达 TAN Ruilong;DUAN Menglan;XU Bin;CHEN Lida(China Ship Research and Development Academy,Beijing 100101,China;College of Safety and Ocean Engineering,China University of Petroleum-Bejjing,Bejjing 102249,China)
出处 《船舶与海洋工程》 2024年第2期1-6,共6页 Naval Architecture and Ocean Engineering
基金 2020年江苏省交通发展重大专项(2020Z02)。
关键词 自升式钻井平台 插桩 拔桩 穿刺 拔桩阻力 jack-up dilling platfom penetration uplift punch-through pile pulling resistance
  • 相关文献

参考文献9

二级参考文献59

共引文献51

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部