摘要
对福建三钢6号高炉大修后开炉达产操作进行了总结。通过设备可靠性运行调试,严格的烘炉操作,充分的试漏试压,精准的开炉料全炉焦比、碱度及装料位置、合理送风参数的选择,对送风后冶炼进程的有效控制,合理的首炉铁时间选择,料制的动态优化等实现了高炉顺利开炉、快速强化达产。
It is summarized the main operating experience in fulfillment of design output of Sansteel No.6 BF after revamping。Through equipment reliability operation commissioning,Strict the drying oven operation,fully the pressure leakage test,accurate selection a blowon program and coke ratio of the whole furnace、alkalinity and charging position,selecting appropriate blowing-in parameters,Effective control of smelting process after blowing-in,Reasonable selection the tapping time of first heat,Dynamic optimization of the charging system,Signifying rapid blowon and rapid design output fulfillment of the furnace.
作者
钟指辉
Zhong Zhihui(Fujian Sansteel Minguang Co.,Ltd.,Sanming 365000,Fujian)
出处
《福建冶金》
2024年第3期20-23,共4页
Fujian Metallurgy
关键词
高炉
大修
开炉
达产
blast furnace
revamping
production
Reaching production capacity