提吊式液压爬模在超高劲性混凝土柱中的应用

Application of Hoisting Hydraulic Climbing Formwork in Ultra-high Steel Reinforced Concrete Column
下载PDF
导出
摘要 深圳市“工业上楼”示范项目红花岭基地项目中高架平台存在超过20 m的超高劲性混凝土柱,基于传统灯笼架防护材料大量留滞、周转效率低等不足,提出采用提吊式液压爬模施工工艺。重点阐述液压爬模的应用场景、安装方式、穿插施工等方面技术要点,最终提高施工效率,节省材料资源。 In Honghualing Base Project,a demonstration project of"Industrial Upstairs"in Shenzhen,there is a ultra-high reinforced concrete column with a height of more than 20 m in the elevated platform.Based on the shortcomings of traditional lantern frame protective materials,such as a large number of retention and low turnover efficiency,the hoisting hydraulic climbing formwork construction technology is proposed.This paper focuses on the application scenarios,installation methods,interspersed construction and other technical points of the hydraulic climbing formwork,which ultimately improves the construction efficiency and saves material resources.
作者 熊宁 胡斌斌 施传浩 李鹏军 王瀚 蒋序君 XIONG Ning;HU Binbin;SHI Chuanhao;LI Pengjun;WANG Han;JIANG Xujun(Shenzhen Construction Engineering Group Co.,Ltd.,Shenzhen 518000,Guangdong,China)
出处 《建筑施工》 2024年第5期790-793,共4页 Building Construction
关键词 工业上楼 高架平台 超高劲性混凝土柱 爬模 industrial upstairs elevated platform ultra-high reinforced concrete column climbing formwork
  • 相关文献

参考文献8

二级参考文献23

共引文献56

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部