摘要 特高压输电线路在我国能源电力战略中起着至关重要的作用。输电线路中的挂点金具、绝缘子等电气设备损毁而造成电力系统瘫痪的情况不在少数。基于新东直流工程实例,从线路覆冰、导线舞动、脱冰跳跃等多个方面分析挂点金具及绝缘子受损原因,同时针对不同的损伤类型给出了相应的整改措施及建议。 Ultra-high voltage(UHV)transmission lines play a crucial role in China's electric energy strategy.There are many cases of power system paralysis caused by damage to hanging point fixtures,insulators,and other electrical equipment in transmission lines.Based on the example of the Xindong DC project,this paper explores the damage caused by hanging point fixtures and insulators from the aspects of line icing,conductor galloping,and ice-shedding jump.Moreover,corresponding countermeasures and suggestions are given for different damage types.
作者 王瑞显 谢中均 李斌明 唐国伟 廖鹏 WANG Ruixian;XIE Zhongjun;LI Binming;TANG Guowei;LIAO Peng(Guangzhou Bureau of China Southern Power Grid Co.,Ltd.,EHV Transmission Company,Guangzhou 510000,China)
出处 《电工技术》 2024年第8期206-209,共4页 Electric Engineering
关键词 输电线路 覆冰损伤 绝缘子 transmission line ice damage insulator
  • 相关文献

参考文献5

二级参考文献58

共引文献287

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部