砂砾卵石覆盖层边坡隧洞进洞方法

Tunnel Entry Method for Slopes Covered with Gravel and Pebble Layers
下载PDF
导出
摘要 以滇中引水工程石鼓水源工程为例,论述砂砾卵石覆盖层边坡隧洞进洞方法。针对砂砾卵石覆盖层边坡稳定性差,隧洞洞口开挖安全风险较高,提出砂砾卵石覆盖层边坡隧洞进洞开挖施工控制措施,通过在孔口两侧边坡打设钢管灌注桩以及自进式超前注浆大管棚,进洞采用预留核心土分台阶开挖法,有效降低隧洞开挖安全风险,提高隧洞进洞施工进度,且满足质量要求。 TakingShigu Water Source Project of Dianzhong Water Diversion Project as an example,this paper discusses the tunnel entry method for slopes covered with sand and gravel.The stability of the slope covered by gravel and gravel is poor,and the safety risk of excavation at the tunnel entrance is relatively high.This article proposes construction control measures for the excavation of tunnels on slopes covered with gravel and gravel.Steel pipe grouting piles and self advancing advance grouting large pipe sheds are installed on both sides of the slope at the hole mouth.The excavation method of reserving core soil and dividing steps is adopted for the tunnel entry.It can effectively reduce the safety risks of tunnel excavation,improve the construction progress of tunnel entry,and meet quality requirements.
作者 董明明 DONG Mingming(POWERCHINA SINOHYDRO ENGINEERING BUREAU 14 CO.,LTD.,Kunming 650041,China)
出处 《云南水力发电》 2024年第S01期62-65,共4页 Yunnan Water Power
关键词 砂砾卵石覆盖层 隧洞洞口开挖 施工质量控制 sand and gravel covering layer excavation of tunnel entrance construction quality contr
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部