摘要
依托云南省已实施完成的金沙江中游6座大型水电站工程建设征地移民安置竣工验收工作实践情况,从验收依据、验收内容以及工作组织管理等方面分析制约水电工程建设征地移民安置竣工验收的主要问题,提出高位推动、调整规划、资金保障、工作大纲、技术支撑、资金清理审计与档案专项验收等工作的成功经验与对策措施。
Based on the practices of resettlement work completion acceptance for six large hydropower projects in the middle reaches of Jinsha River in Yunnan Province,the main problems restricting the completion acceptance are summarized and analyzed from the aspect of acceptance basis,acceptance content,and work organization and management.The successful experiences and measures are put forward to promote the complete acceptance,planning adjustment,fund guarantee,work outline,technical support,fund liquidation audit and special acceptance of archives.
作者
郭瑾瑜
王奎
文良友
GUO Jinyu;WANG Kui;WEN Liangyou(China Renewable Energy Engineering Institute,Beijing 100120,China)
出处
《水力发电》
CAS
2024年第6期12-16,共5页
Water Power
关键词
水电工程
移民安置竣工验收
经验与对策
金沙江中游
hydropower project
resettlement work completion acceptance
experience and measures
the middle reaches of Jinsha River