悬臂挂篮施工作为大跨度变截面连续箱梁常用的施工方法,被广泛应用于高速公路、铁路桥梁中。但其施工工期较长,且对施工空间有一定要求,部分项目仍有变更为大节段现浇的需求。文章以某(40+60+40)m变截面连续箱梁为例,详细说明了变更施工方案后的构造该如何重新设计,并分析了两种施工方案的结构受力差异,以期为同类桥梁变更提供参考。
As a common construction method of long-span variable cross-section continuous box girder,cantilever hanging basket construction is widely used in highway and railway bridges.However,its construction period is long,and there are certain requirements for construction space.Some projects still need to be changed to large-segment castin-place.Taking a(40+60+40)m variable cross-section continuous box girder as an example,this paper explains in detail how to redesign the structure after changing the construction scheme,and analyzes the structural stress difference between the two construction schemes.It is hoped that this study will provide reference for similar bridge changes.
作者
胡哲
蒋兴法
曹硕
HU Zhe;JIANG Xingfa;CAO Shuo(Zhejiang Institute of Communications Co.,Ltd.,Hangzhou 310030,Zhejiang,China)
出处
《工程技术研究》
2024年第6期9-11,共3页
Engineering and Technological Research
关键词
悬臂挂篮施工
大节段支架现浇
构造设计
结构验算
cantilever hanging basket construction
cast-inplace large segment bracket
structural design
structural checking