摘要 随着市政道路工程逐渐完善,隧道断面不断增大,常面临超大断面浅埋软弱围岩的施工工况,对隧道施工提出更高的要求。本文经过对常见施工方法的分析,结合某工程项目对隧道施工方法进行详细阐述,通过建立双侧壁导坑法模型以及交叉中隔壁法模型,对两种工法进行比对,关注围岩位移的监测,控制支护变形以及地面沉降等问题,选择最佳施工工法。 With the gradual improvement of municipal road engineering,the tunnel section continues to increase,often facing construction conditions of super large section shallow buried weak surrounding rock,which puts forward higher requirements for tunnel construction.This article analyzes common construction methods and provides a detailed explanation of tunnel construction methods in conjunction with a certain engineering project.By establishing models of double-sided wall heading method and cross middle partition method,the two methods are compared,focusing on monitoring surrounding rock displacement,controlling support deformation and ground settlement,and selecting the best construction method.
作者 许世豪 Xu Shihao(Zhongyifeng Construction Group Co.,Ltd.,Suzhou,China)
出处 《科学技术创新》 2024年第11期125-128,共4页 Scientific and Technological Innovation
关键词 超大断面 软弱围岩 市政隧道 施工方案 super large cross-section weak surrounding rock municipal tunnels construction plan
  • 相关文献

参考文献3

二级参考文献17

共引文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部