Construction of shallow buried large-span metro stations using the small pipe roof-beam method

原文传递
导出
摘要 In relation to the Shifu Road Station project on Line 4 of the Shenyang Metro in China,a small-pipe roof-beam method for constructing subway stations is presented.First,a numerical simulation was performed to optimize the supporting parameters of the proposed method and determine the design scheme.Subsequently,the deformation of the pipe roof and surface settlement during the construction process were investigated.Finally,the surface settlement attributed to the excavation was studied through field monitoring,and the proposed method was compared with other methods.The results show that an increase in the pipe-roof spacing has little effect on the surface settlement and piperoof deformation.The bearing capacity of the pipe roof can be efficiently utilized once the flexural stiffness reaches 2EI,and the flexural stiffness is not the dominant factor controlling the deformation.The essential stages in controlling surface settlement are the excavations of the transverse pilot tunnels and the soil between them.The final settlement value of the ground was 24.1 mm,resulting in a reduction in the construction period by at least five months while satisfying the control requirements.
出处 《Frontiers of Structural and Civil Engineering》 SCIE EI CSCD 2024年第1期122-136,共15页 结构与土木工程前沿(英文版)
基金 supported by the National Natural Science Foundation of China(Grant No.52108380) the Natural Science Foundation of Jiangsu Province of China(No.BK20210721) the Postdoctoral Research Foundation of China(No.2021M702400).
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部