摘要
为研究公路隧道开挖初期支护阶段的变形特性,论文以云南宁永高速公路哨坪隧道为工程背景,采用有限元计算软件Midas GTS对哨坪隧道初期支护变形段进行数值模拟,并结合隧道监控量测数据,分析其变形规律,提出初期支护变形段处治方案并评价其支护效果。
In order to study the deformation characteristics of the initial support stage of highway tunnel excavation,taking Shaoping Tunnel of Ningyong Expressway in Yunnan Province as the engineering background,the finite element calculation software Midas GTS is used to simulate the initial support deformation section of Shaoping tunnel,and combined with the tunnel monitoring and measurement data,its deformation law is analyzed.The treatment scheme of deformation section of initial support is put forward and its supporting effect is evaluated.
作者
田冲冲
刘浏
贾占胜
TIAN Chong-chong;LIU Liu;JIA Zhan-sheng(Beijing Jiaoke Transport Consultants Ltd.,Beijing 100191,China)
出处
《工程建设与设计》
2024年第11期89-91,共3页
Construction & Design for Engineering
关键词
隧道工程
围岩变形
数值模拟
处治方案
tunnel engineering
surrounding rock deformation
numerical simulation
treatment plan