期刊文献+

MORACICA大桥墩身爬模施工中混凝土外观质量控制

Quality Control of Concrete Appearance of Pier Shaft during Climbing Construction of MORACICA Bridge
原文传递
导出
摘要 黑山南北高速公路项目MORACICA大桥P1~P5桥墩分为两种类型:P2~P4为中主墩,结构形式为上部90m范围采用双薄壁断面,下部区域采用箱形断面;P1、P5桥墩采用双薄壁形式。大桥横跨当地欧洲八国主干线——E80国道,故大桥的外观成为了各界关注的焦点,在MORACICA大桥墩身爬架混凝土施工中采取了有效控制措施,加强对混凝土表面平整度、光泽度、墩身棱角的质量控制以及混凝土外观成品保护,提升了MORACICA大桥外观质量和社会影响力。 The piers of the MORACICA Bridge on the Smokovac-Uvac-Matesevo Highway Project is divided into two types:the main pier P2~P4 is with the structure of double thin-walled section for the top 90 m,and of box section for the lower part;the Pl,P5 piers are double thin-walled section.The Bridge crosses E8o Highway,the main trunk road for eight countries,thus its appearance has become the focus of concern.During the climbing formwork concrete construction of pier shaft of the MORACICA Bridge,the smoothness,gloss,edges of piers,and the appearance of the finished product are the focus of technical control so as to improve the appearance of the bridge quality and social influence.
作者 赵成立 马金强 邓智文 ZHAO Cheng-li;MA Jin-qiang;DENG Zhi-wen(CCCC-SHEC Fourth Engineering Company Limited,Wuhu 241000,China)
出处 《公路》 北大核心 2024年第2期84-86,共3页 Highway
关键词 桥梁工程 混凝土外观 爬模施工 平整度 光泽度 墩身棱角 成品保护 bridge engineering climbing form construction concrete appearance smoothness gloss edges of pier shaft protection of finish
  • 相关文献

参考文献5

二级参考文献16

共引文献28

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部