配电网施工人力机械资源科学调配模型与方法

Model and Method for Scientific Allocation of Human and Mechanical Resources in Distribution Network Construction
下载PDF
导出
摘要 [目的]随着配网建设投资规模屡创新高,工程项目与日俱增,配网工程项目的项目进度管控和项目管理面临着巨大压力,为了实现全过程管控与资源相结合,全面提升配电网施工管理水平,配电网施工人机资源科学调配的研究具有重要意义。[方法]首先,通过调研梳理各流程环节的先后逻辑关系,采用单代号有向网络图建立了配电网工程项目各工序的流程模型;然后,基于项目全过程工期影响因素的分析,构建了施工阶段指导工期测算模型;最后,提出了基于遗传算法的配电网施工人力机械资源科学调配方法,为项目全过程在时间维度上的不同种类的人力机械设备资源分配提供数据支持,实现资源最优分配并预测工期。[结果]根据某配网实际工程项目构建算例,对所提方法的有效性进行了分析,结果表明所提方法有效缩短了施工工期,并且可得出重要资源的每日分布情况以及项目关键路径,为进一步缩短工程工期提供理论指导。[结论]可见,所提方法有效实现了资源调配、辅助管理者决策的目的,同时提高了资源的利用率,间接减少不必要的资源成本,提高项目整体的工作效率。 [Introduction]With the increasing scale of investment in distribution network construction and the increasing number of engineering projects,there is considerable pressure on project progress control and project management in distribution network engineering projects.In order to achieve the control and management throughout the process and integrate resources,and to comprehensively improve the management level of distribution network construction,the research on scientific allocation of human and mechanical resources in distribution network construction is of great significance.[Method]Firstly,through research and analysis of the logical relationships of various process links,the activity-on-node directed network diagram was used to establish a process model for each process of the distribution network engineering project;then,based on the analysis of factors affecting the project construction period in the whole process,a model for guiding the calculation of the construction period in the construction phase was established;finally,a scientific allocation method for human and mechanical resources in distribution network construction based on the genetic algorithm was proposed.The method provided data support for the allocation of different human and mechanical equipment resources throughout the project process in the time dimension,enabling optimal resource allocation and construction period prediction.[Result]Based on a practical engineering project in a certain distribution network,a case study is constructed to analyze the effectiveness of the proposed method.The results show that the utilization of the proposed method can effectively shorten the construction period,and offer the daily distribution information of important resources and the critical path of the project,providing theoretical guidance for further shortening the engineering period.[Conclusion]It can be seen that the proposed method effectively achieves the goals of resource allocation and assisting managers in decision-making,while increasing the resource utilization rate,indirectly reducing unnecessary resource costs,and improving the overall work efficiency of the project.
作者 马彬 肖俊阳 吴新 罗金阁 宋佳刚 徐展鹏 MA Bin;XIAO Junyang;WU Xin;LUO Jinge;SONG Jiagang;XU Zhanpeng(Shenzhen Power Supply Bureau Co.,Ltd.,Shenzhen 518000,Guangdong,China;China Energy Engineering Group Guangdong Electric Power Design Institute Co.,Ltd.,Guangzhou 510663,Guangdong,China)
出处 《南方能源建设》 2024年第S01期36-46,共11页 Southern Energy Construction
基金 深圳供电局有限公司科技项目“配网工程项目全过程管控决策辅助研究”(090000KK52222063)。
关键词 配电网 项目施工工期 遗传算法 优化模型 科学调配 distribution network project construction period genetic algorithm optimization model scientific allocation