摘要
在顶推法施工过程中,桥梁的体系转换频繁,结构受力比其他施工方式复杂,施工安全风险也随之增大,因此,选择适用于钢箱梁安全有效的顶推施工方案和施工技术尤为关键。论文结合春江枢纽A匝道桥钢箱梁顶推施工,对顶推施工方案进行了精细化划分,并从关键技术、施工流程、施工控制等方面对顶推施工技术进行系统介绍。
In the process of jacking construction,the bridge system is frequently changed,the structural force is more complicated than other construction methods,and the construction safety risk is also increased.Therefore,it is particularly critical to select the safe and effective jacking construction scheme and construction technology suitable for steel box girder.Based on the steel box girder jacking construction of A ramp bridge in Chunjiang Junction,the paper divides the jacking construction scheme and introduces the jacking construction technology systematically from key technology,construction process and construction control.
作者
陈云平
CHEN Yun-ping(Changzhou Communications Construction Administration Co.Ltd.,Changzhou 213001,China)
出处
《工程建设与设计》
2024年第13期197-199,共3页
Construction & Design for Engineering
关键词
钢箱梁
顶推施工
步履式三向千斤顶
steel box girder
jacking construction
walking three-way jack