摘要
肥城市是典型的缺水城市,化工产业园的生产用水以地表水为主。肥城市再生水厂二期工程主要为工业企业供水,总设计供水规模为5.0万m^(3)/d,近期设计供水规模为2.5万m^(3)/d。分析再生水厂二期工程的工艺方案选择,详细说明构筑物设计参数,可以为类似项目设计提供参考。经评估,再生水厂二期工程的建设可以满足现状工业企业用水需求,达到预期效果。
Feicheng city is a typical water scarce city,and the production water for the chemical industry park is mainly surface water.The phaseⅡproject of a regenerated water plant in Feicheng city mainly provides water for industrial enterprises,with a total designed water supply scale of 50000 m^(3)/d and a recent designed water supply scale of 25000 m^(3)/d.Analyzing the process plan selection for the phaseⅡproject of the regenerated water plant and providing detailed explanations of the structural design parameters can provide reference for similar project designs.After evaluation,the construction of the phaseⅡproject of the regenerated water plant can meet the current water demand of industrial enterprises and achieve the expected results.
作者
褚帆
孙丕超
CHU Fan;SUN Pichao(Shandong Branch of China Urban Construction Design&Research Institute Co.,Ltd.,Jinan 250000,China)
出处
《中国资源综合利用》
2024年第6期272-274,共3页
China Resources Comprehensive Utilization
关键词
再生水厂
工程设计
肥城市
regenerated water plant
project design
Feicheng city