摘要
珠海机场综合交通枢纽项目一期工程屋盖钢结构工程,具有规模大、结构形式复杂、造型精致等特点。采用地面预拼装、分段吊装施工工艺,并对桁架预拼装、直线度及垂直度等进行测量及监测,较好地完成了屋盖钢结构安装,保证了安装精度。相比传统施工工艺,该施工工艺有效降低了施工成本。
The roof steel structure project of Zhuhai Airport comprehensive transportation hub project phaseⅠhas the characteristics of large scale,complex structural form and exquisite shape.The construction technology of ground pre-assembly and segmented hoisting is adopted,and the pre-assembly,straightness and perpendicularity of truss are measured and monitored.The installation of roof steel structure is completed well and the installation accuracy is ensured.Compared with the traditional construction technology,the construction technology effectively reduces the construction cost.
作者
唐明成
冯声法
张波
袁龙彬
连伟佳
屈利鹏
李子凯
张四伟
TANG Mingcheng;FENG Shengfa;ZHANG Bo;YUAN Longbin;LIAN Weijia;QU Lipeng;LI Zikai;ZHANG Siwei(Zhuhai Branch of China Construction Second Engineering Bureau Co.,Ltd.,Zhuhai,Guangdong 519000,China)
出处
《施工技术(中英文)》
CAS
2024年第14期72-76,共5页
Construction Technology
关键词
钢结构
屋盖
桁架
网架
吊装
提升
滑移
steel structures
roofs
trusses
grids
hoists
lifting
slipping