摘要
抗浮锚杆造价低、经济效益好、抗浮作用明显,地下室抗浮设计首先考虑抗浮锚杆,当潜孔钻机穿过承压水层时,地下水呈弱承压性,成孔处大量地下水以0.1 m~3/s的速度向外涌出,简单的防堵措施收效甚微。经研究后决定先施工地下室底板,后施工抗浮锚杆,有效避免了地下水上涌对抗浮锚杆施工的影响。抗浮锚杆于筏板后施工,有效克服了在地下室结构中预留孔洞后封堵等质量通病。
When the groundwater is over-pressurized,it will endanger the main structure of buildings.Since anti-floating anchors have low cost,good economic returns and obvious anti-floating effect,they are preferred in the anti-floating design of basements.When the down-the-hole drill passes through the artesian aquifer,the groundwater is weakly pressurized.A large amount of groundwater gushes out at a rate of 0.1 m3/s at the hole.Simple anti-clogging measures have poor effect.The Project Management Department decides after deliberation to construct the basement floor first and then anti-floating anchors.This can effectively avoid the influence of groundwater upwelling on the construction of anti-floating anchors.The anti-floating anchor is constructed after the raft,effectively overcoming such common quality problems as blocking after reserving holes in the basement structure.
作者
刘毅
LIU Yi(Wuhan Construction Group Co.,Ltd.,430000,Wuhan,China)
出处
《建筑技术》
2024年第15期1825-1828,共4页
Architecture Technology
关键词
抗浮锚杆
筏板施工
地下水管涌
降低成本
anti-floating anchors
construction of the raft
groundwater pipe surge
reduce cost