摘要
我国的水库大坝多数已完成过一次安全鉴定或除险加固,运行状态和安全性状有所改变,近期进入了新一轮的安全评价周期。随着新的大坝安全评价导则及相关标准的实施,对大坝安全评价提出了一些新的要求。在新一轮的大坝安全评价工作中,不同的评价单位对一些常见技术问题作出了不同判断,导致安全评价结论大相径庭,也影响了后续的除险加固工作。本文对照新导则的基本技术要求,对这些常见的技术问题进行了梳理,剖析问题的本质,以利于提高大坝安全评价的准确性。
Most of the reservoir dams in China have completed a safety appraisal or reinforcement,so their operation state and safety have changed to certain extent.They recently enter a new round of safety evaluation cycle.With the implementation of new dam safety evaluation guideline and relevant standards,there are new requirements for dam safety evaluation.During the new round of dam safety evaluation,different evaluation units have made different judgments on some common technical problems,resulting in vastly different conclusions of safety evaluation,affecting the subsequent reinforcement work.The author compared the basic technical requirements of new and old guidelines,sorted out the frequently seen technical problems,analyzed the nature of the problem,aiming to improve the accuracy of dam safety evaluation.
作者
赵国理
方业源
ZHAO Guo-li;FANG Ye-yuan(Nanning Dawangtan Reservoir Management Office Nanning 530202,China;Guangxi Guiyu Engineering Consultant Co.,Ltd.,Nanning 530023,China)
出处
《广西水利水电》
2024年第4期107-111,共5页
Guangxi Water Resources & Hydropower Engineering
关键词
小型水库
土石坝
安全评价
除险加固
主要技术
small-scale reservoir
earth-rock dam
safety evaluation
reinforcement
main technologies