摘要
以西门子燃气轮机作为原动机的案例,论述燃气轮机在场地仓储、安装定位、调试准备及调试过程中的典型问题和流程。结合国内适用法规和通用规范,对燃气轮机在国内规范及标准方面进行阐述和分析,提出针对现场第三方检验的建议,为开展相关工作提供指导。
Taking the Siemens gas turbine as prime mover,the typical problems and processes in site storage,installation positioning,preparation for commissioning and commissioning process of the gas turbine were discussed.Combined with the applicable domestic laws and regulations and general standards,the domestic regulations and standards of gas turbines were expounded and analyzed;suggestions for the on-site third-party inspection were put forward,so as to provide practical guidance for the relevant work.
作者
程超
CHENG Chao(Zhanjiang Branch of China Classification Society,Zhanjiang Guangdong 524022,China)
出处
《船海工程》
北大核心
2024年第S01期37-40,共4页
Ship & Ocean Engineering
关键词
燃气轮机
场地管理
定位安装
附属系统
调试试验
gas turbine
site management
positioning and installation
auxiliary system
commissioning test