摘要 介绍了旭龙水电站导流洞工程地质概况、安全监测设计和监测施工,通过对围岩变形、渗压渗流、应力应变和温度等监测数据的采集分析,对导流洞洞身的稳定性、安全度做出评价,系统掌握导流洞施工开挖过程围岩的变形与应力应变规律。施工期安全监测在施工过程中起到了反馈设计与指导施工的良好作用。 The paper presents the engineering geological conditions,safety monitoring design,and monitoring construction of the diversion tunnel at Xulong Hydropower Station.Through the collection and analysis of data on deformation,seepage pressure,stress and strain,and temperature of surrounding rock,the stability and safety level of the tunnel structure are evaluated.The deformation and stress-strain patterns of surrounding rock during construction and excavation of the diversion tunnel are systematically understood.Safety monitoring during construction plays a crucial role in providing feedback for design adjustments and guidance during construction.
作者 吴双利 WU Shuang-li(CHN Energy Jinsha River Xulong HydroPower Co.,Ltd.,Chengdu 610041,China)
出处 《价值工程》 2024年第25期61-64,共4页 Value Engineering
关键词 旭龙水电站 导流洞 安全监测 变形分析 Xulong Hydropower Station diversion tunnel safety monitoring deformation analysis
  • 相关文献

参考文献3

二级参考文献17

共引文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部