摘要
为了解决煤矿综采工作面存在的安全隐患问题,需要对工作面过断层围岩控制技术进行合理应用。基于此,本文结合某综采工作面案例展开分析,结合实际过断层地质条件情况,提出注浆加固设计方案,采取注浆加固效果数值模拟分析,最终保证综采工作面过断层的加固工作效果,为后续的煤矿安全开采工作打下良好的基础,同时希望可以为相关工作开展提供有效参考。
In order to solve the safety hazards of coal mine fully mechanized mining faces,it is necessary to apply reasonable control technology for the surrounding rock passing through faults in the working face.Based on this,this article combines a case study of a fully mechanized mining face and proposes a grouting reinforcement design scheme based on the actual geological conditions of the fault crossing.Numerical simulation analysis of the grouting reinforcement effect is adopted to ultimately ensure the reinforcement effect of the fully mechanized mining face crossing the fault,laying a good foundation for subsequent coal mine safety mining work.At the same time,it is hoped that this can provide effective reference for related work.
作者
郭俊斌
Guo Junbin(Safety Supervision Center of Shanxi Fenxi Mining(Group)Co.,Ltd.,Jiexiu Shanxi 032000,China)
出处
《山西化工》
CAS
2024年第8期207-209,共3页
Shanxi Chemical Industry
关键词
煤矿
综采工作面
过断层
围岩控制
coal mine
fully mechanized mining face
passing through faults
surrounding rock control