摘要 上海有机化学研究所临港园区项目在外墙外保温施工过程中面临着多项挑战,如保温材料质量、施工质量控制和施工技术支持等。针对这些问题,论文以上海有机化学研究所临港园区项目为例,深入分析了外墙外保温施工过程中存在的问题及其技术对策。通过对该项目的具体实践和研究,旨在提升外墙外保温系统的质量和性能,确保建筑节能效果的实现。 The Lingang Park project of Shanghai Institute of Organic Chemistry faces many challenges in the construction process of external wall insulation,such as the quality of thermal insulation materials,construction quality control and construction technical support.In view of these problems,this paper takes the Lingang Park project of Shanghai Institute of Organic Chemistry as an example,and deeply analyzes the problems existing in the construction process of external wall insulation and its technical countermeasures.Through the specific practice and research of the project,it aims to improve the quality and performance of the external wall insulation system,and ensure the realization of the building energy saving effect.
作者 史磊平 Leiping Shi(Shanghai Wentian Construction Engineering(Group)Co.,Ltd.,Shanghai,225700,China)
出处 《工程设计与施工》 2024年第8期4-6,共3页 Engineering Design and Construction
关键词 外墙外保温 保温层施工 基层处理 external wall insulation insulation layer construction base treatment
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部