一起110 kV GIS开关合闸瞬间交直流窜电故障分析

Analysis of AC-DC Transient Overvoltage Fault During 110 kV GIS Switching Operation
下载PDF
导出
摘要 交直流窜电是变电站直流系统中较为严重的接地故障,极有可能造成保护误动或拒动,严重影响供电可靠性。针对某实际运行的110 kV变电站交直流窜电故障,首先结合保护动作、故障录波情况给出了事故原因分析与故障排查过程;然后进一步结合二次原理图与现场接线情况提出了整改方案,并验证了整改后回路的安全性;最后给出了此类故障的预防措施与建议,可为防范交直流窜电引起保护误动、拒动提供参考。 AC-DC transient overvoltage is a severe grounding fault in the DC systems of substations,which can potentially lead to incorrect operation or failure of protection devices,seriously affecting power supply reliability.This paper analyzes a case of AC-DC transient overvoltage fault occurring during the switching operation of a 110 kV substation.Initially,the analysis of the accident cause and fault investigation process is presented based on protection actions and fault waveform records.Subsequently,a rectification plan is proposed combining secondary schematic diagrams and on-site wiring conditions to validate the safety of the revised circuit.Finally,preventive measures and recommendations for avoiding protection misoperation and failure due to AC-DC transient overvoltage are provided.
作者 周平 方苏 闫童 俞玲 沈良 李启本 ZHOU Ping;FANG Su;YAN Tong;YU Ling;SHEN Liang;LI Qiben(State Grid Songjiang Power Supply Company,SMEPC,Shanghai 201600,China)
出处 《电力与能源》 2024年第4期521-524,共4页 Power & Energy
关键词 交直流窜电 直流接地 故障分析 AC-DC transient overvoltage DC grounding fault analysis
  • 相关文献

参考文献6

二级参考文献39

共引文献21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部