跨江涉水大型建设项目安全管理能力成熟度评价研究

Research on Maturity Evaluation of Safety Management Capability in Large-Scale River-Crossing and Water-Involved Construction Projects
下载PDF
导出
摘要 为准确评价跨江涉水大型建设项目中总承包企业的安全管理水平,采用成熟度模型及模糊层次分析(F-AHP)定量评价方法,参考国内外重大建设项目安全管理的先进做法,确定重大建设项目安全管理要素,建立起7个一级指标、30个二级指标的评价体系,以重庆某跨江特大型悬索桥为研究案例,深入研究其总承包企业对大型建设项目的安全管理能力的成熟度。研究表明,当前阶段其安全管理水平处于管理级,符合现场实际情况,证明具有可行性。此安全管理成熟度评价体系的形成及评价方法的应用,对类似跨江特大型悬索桥或类似跨江涉水重大项目安全管理现状的阶段性评价具有借鉴意义。 To accurately assess the safety management level of general contractors in large-scale cross-river and water-related construction projects,this study adopts a maturity model and a quantitative evaluation method based on Fuzzy Analytic Hierarchy Process(F-AHP).By referring to advanced practices in safety management of major construction projects both domestically and internationally,the key elements of safety management for such projects are identified.An evaluation system comprising seven first-level indicators and 30 second-level indicators is established.Taking a specific case of an extra-large suspension bridge across a river in Chongqing,this study delves into the maturity of safety management capabilities of the general contractor for this large-scale construction project.The research reveals that the current safety management level falls within the"management level"consistent with the actual situation on site,demonstrating its feasibility.The formation of this safety management maturity evaluation system and the application of the evaluation method provide valuable insights for the staged evaluation of safety management status in similar extra-large suspension bridges across rivers or other significant cross-river and water-related projects.
作者 张学堃 ZHANG Xuekun
出处 《重庆建筑》 2024年第S01期23-26,共4页 Chongqing Architecture
关键词 安全管理 成熟度模型 跨江特大型悬索桥 模糊层次分析法 Safety Management Maturity Model Extra-large Suspension Bridge Across River Fuzzy Analytic Hierarchy Process(F-AHP)
  • 相关文献

参考文献6

二级参考文献61

  • 1李健旋.中国制造业智能化程度评价及其影响因素研究[J].中国软科学,2020(1):154-163. 被引量:81
  • 2黄顺春,张书齐.中国制造业高质量发展评价指标体系研究综述[J].统计与决策,2021(2):5-9. 被引量:31
  • 3刘建立,覃维祖,李飞.用新成熟度概念预测混凝土早期强度应用研究[J].施工技术,2006,35(8):68-70. 被引量:6
  • 4Badenfelta U. I Trust You, I Trust You not : A Longitudinal Study of Control Mechanisms in Incentive Contracts [ J ]. Construction Man- agement and Economics,2010,28(3) :301 - 310.
  • 5Loosemore M, McCarthy C S. Perceptions of Contractual Risk Alloca- tion in Construction Supply Chains [ J ]. Journal of Professional Issues in Engineering Education and Practice,2008,134 ( 1 ) : 95 - 105.
  • 6Laan A T. Building Trust:The Case of the Construction Industry [ D]. Twente : The University of Twente,2009.
  • 7Girmscheid G, Brockmann C. Inter-and Intraorganizational Trust in Intemational Construction Joint Ventures [ J ]. Joumal of Construction Engineering and Management ,2010,136 ( 3 ) : 353 - 360.
  • 8Chetmg S O, et al. Deve|oping a Trust Inventory for Construction Contracting[ J ]. International Journal of Project Management, 2011, 29(3) :184 - 196.
  • 9Tuuli M, Rowlinson S, Koh T. Dynamics of Control in Construction Project Teams[ J]. Construction Management and Economics,2010, 28(2) :189 -202.
  • 10Ling F Y Y ,Tran H B T. Ingredients to Engender Trust in Construc- tion Project Teams in Vietnam J ]. Construction Innovation : Informa- tion, Process, Management,2012,12 ( 1 ) :43 - 61.

共引文献67

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部