摘要
溢洪道是水库工程中十分重要的泄洪建筑物,在参与水资源的调度工作中直接影响人民的生命财产安全。但溢洪道在施工及后期运营期间,其工作闸会产生各种问题,文章结合河口村水库运营过程中工作闸产生的故障,提出采取的针对性处理措施,可为其他水库工作闸故障提供一定的参考依据。
Spillway is a very important flood releasing structure in reservoir engineering,which would directly affect the safety of people's lives and property in reservoir regulation.However,during the construction and later operation of the spillway,various problems may arise with its service gate.This paper analyzes the faults that occurred during the operation of the service gate in Hekoucun Reservoir and proposes targeted treatment measures,which could be used for reference for treatment of service gate faults of other reservoirs.
作者
任杰
REN Jie(Hekoucun Reservoir Operation Center,Henan Province,Jiyuan 454650,China)
出处
《河南水利与南水北调》
2024年第8期71-72,共2页
Henan Water Resources & South-to-North Water Diversion
关键词
水库
溢洪道
工作闸
故障
措施
reservoir
spillway
service gate
fault
measures