对某工程实例工序优化前后2次试验桩的单桩承载力特征值进行了研究,验证了当承载力检测值不满足设计要求时,通过增加后注浆及刷壁器“破壁”等工序,能够有效提高在桩端持力层起伏较大的情况下的单桩竖向抗拔承载力。
This article studied the bearing capacity characteristic value of two test piles before and after process optimization of a project example,and it is verified that when the bearing capacity test value does not meet the design requirements,the vertical uplift bearing capacity of a single pile can be effectively improved under the condition of large fluctuation of the bearing layer at the pile end by adding post-grouting and addingthe wall brush to“break the wall”.
作者
方文全
王伟
胡纬中
FANG Wen-quan;WANG Wei;HU Wei-zhong(China Construction First Engineering Group South China Construction Co.Ltd.,Shenzhen 518040,China)
出处
《工程建设与设计》
2024年第20期7-9,共3页
Construction & Design for Engineering
关键词
试验桩
单桩抗拔承载力特征值
持力层
后注浆
刷壁器“破壁”
test pile
characteristic value ofsingle pile uplift bearingcapacity
bearinglayer
post grouting
wall scrubber“breaking”