浅析岩滩水电站4号机组轴线超标处理

Treatment on Axis Exceeding Standard for Unit 4 in Yantan Hydropower Station
下载PDF
导出
摘要 针对岩滩水电站4号机组轴线超标的问题,笔者结合轴线结构特点,分析问题原因,提出轴线超标处理方法及处理过程,并阐述轴线调整实施情况。结果表明,处理后机组摆度达到标准允许值要求,消除了岩滩水电站4号机组轴线超标这一重大隐患,可为后续机组同类型问题处理提供参考。 In view of the problem of the axis exceeding the standard for Unit 4 in Yantan Hydropower Station,the author analyzes the causes of the problem in combination with the characteristics of the axis structure,puts forward the treatment method and process of the axis exceeding the standard,and expounds the implementation of the axis adjustment.The results show that the swing of the unit after treatment meets the requirements of the standard allowable value,which eliminates the major hidden danger of the axis exceeding the standard for Unit 4 in Yantan Hydropower Station,and can provide reference for the subsequent handling of similar problems in the unit.
作者 赵文博 ZHAO Wenbo(Datang Yantan Hydropower Co.,Ltd.,Dahua 530811,China)
出处 《红水河》 2024年第5期150-155,共6页
关键词 轴线 超标 盘车 推力轴承 处理 岩滩水电站 axis exceeding standard barring thrust bearing treatment Yantan Hydropower Station
  • 相关文献

参考文献1

二级参考文献4

共引文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部