摘要
针对重庆山区隧道工程中大断面软弱围岩的开挖问题,研究分析了现有单侧壁导坑法在施工稳定性和成本控制方面的局限性,优化了单侧壁导坑法,通过移除部分支撑结构并增设钢板来提升结构稳定性,实施了3台阶7步开挖法,有效控制了围岩变形。
In response to the excavation problem of large section weak surrounding rock in tunnel engineering in mountainous areas of Chongqing,the limitations of the existing single side wall heading method in construction stability and cost control were studied and analyzed.The single side wall heading method was optimized by removing some supporting structures and adding steel plates to improve structural stability.The three-bench seven-step excavation method was implemented to effectively control the deformation of the surrounding rock.
作者
王磊
王晓峥
李文浩
WANG Lei;WANG Xiao-zheng;LI Wen-hao(China Construction Third Bureau Group Co.Ltd.,Wuhan 430070,China)
出处
《工程建设与设计》
2024年第21期96-98,共3页
Construction & Design for Engineering
关键词
单侧壁导坑法
围岩变形
隧道施工
数值模拟
single side wall guide pit method
surrounding rock deformation
tunnel construction
numerical simulation