摘要
介绍了外地施工单位首次从事上海软土深基坑施工运用时空效应原理,在监测数据的基础上,调正施工参数,组织"三快"施工,建立起新的平衡,达到了一级环境保护的设计要求,可给我们一些有益的启迪。
The Construction organization applied the time-space effect theory, during the construc- tion of the deep excavation in Shanghai soft clay stratum. Under the guide of the monitored data, the construction organization adjusted the construction parameters, established the new balance and achieved the design requirements for the first environment protection grade.