摘要
针对目前招投标项目中 ,大型机组凝汽器冷却面积选取有越取越大的趋势 ,笔者从凝汽器设计和运行积累经验出发 ,描述合理选取凝汽器冷却面积的必要性以及单、双背压凝汽器选定的原则。表 1参
Presently, in power plant bidding, there is a trend that the owners have new requirements of selection large cooling surface for condenser. The author, based on his accumulated experiences in the design and operation of condensers, describes the main principles and necessity of reasonably selecting cooling surface of condenser, and the type of single/dual pressure condensers.Table 1 and refs 3.
出处
《动力工程》
CSCD
北大核心
2002年第6期2096-2098,2053,共4页
Power Engineering