具有简单线性恶化加工时间的Flow shop调度问题 被引量:2

Flowshop Scheduling Problem Under Linear Deterioration
下载PDF
导出
摘要 讨论工件具有简单线性恶化加工时间的FlowShop调度问题·对于两台机器目标函数为极小化最大完工时间的FlowShop调度问题 ,证明了利用Johnson规则可以求得最优调度·对于多台机器的一般FlowShop调度问题 ,如果工件在各机器上的加工时间均相等 ,目标函数为极小化最大完工时间或最大延误的问题可以转化为单机调度问题·如果目标函数为极小化完工时间和 ,则利用SPT规则可以求得最优调度· The Flow shop scheduling problem under simple linear deterioration was considered. For the two machine flowshop scheduling Johnson′s rule yields optimal schedule to minimize makespan. If the processing time of job on each of the machines are equal for flowshop, the problem can be deduced to single machine scheduling problem when the objective is the makespan or the maximum lateness and the SPT rule is optimal to minimize the sum of completion times.
出处 《东北大学学报(自然科学版)》 EI CAS CSCD 北大核心 2002年第9期837-839,共3页 Journal of Northeastern University(Natural Science)
基金 辽宁省科技厅自然科学基金资助项目 (9910 70 0 1) 辽宁省教育厅高等学校科学研究项目 (2 0 2 62 2 5 0 99112 15 5 8)
关键词 加工时间 FLOWSHOP 最优调度 线性恶化 最大完工时间 工件 单机调度 Jonson规则 scheduling single machine flow shop linear deterioration makespan sum of completion times
  • 相关文献

参考文献10

  • 1Yang D L,Chern M S.A generalized two-machine flowshop scheduling problem with processing time linearly dependent on job waiting-time[].Computers and Industrial Engineering.1999
  • 2Browne S,Yechiali U.Scheduling deteriorating jobs on a single processor[].Operations Research.1990
  • 3Sundararaghavan P S,Kunnathur A S.Single machine scheduling with start time dependent processing times: some solvable cases[].European Journal of Operational Research.1994
  • 4Bachman A,Janiak A.Minimizing maximum lateness under linear deterioration[].European Journal of Operational Research.2000
  • 5Alidaee B,Womer NK.Scheduling with time dependent processing times: review and extensions[].Journal of the Operational Research Society.1999
  • 6Alidaee B.Single machine scheduling with nonlinear cost functions[].Computers and Operations Research.1991
  • 7Gupta J N D,Gupta S K.Single facility scheduling with nonlinear processing times[].Computers and Industrial Engineering.1988
  • 8Mosheiov G.Scheduling jobs under simple linear deterioration[].Computers and Operations Research.1994
  • 9Kunnathur A S,Gupta S K.Minimizing the makespan with late start penalties added to processing time in a single facility scheduling problem[].European Journal of Operational Research.1990
  • 10Cheng T C E,Ding Q.Single machine scheduling with stepdeteriorating processing times[].European Journal of Operational Research.2001

同被引文献24

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部