预应力混凝土连续梁悬臂浇筑施工工艺及控制要点 被引量:2

Cantilevered Casting Technology and Control Points for the Construction of Continuous PC Beam
下载PDF
导出
摘要 结合马泽拉斯特大桥主桥(40+64+40)m预应力混凝土连续梁的悬臂浇筑施工,简要阐述了悬臂浇筑的工艺及施工过程中0#块的施工、挂篮、预应力张拉、合龙段施工、线形调整等关键控制点所采取的措施。论文阐述的控制要点及相应措施确保了悬臂施工的进度和质量,并保证最终成桥后的线形和内力都符合设计要求,为悬臂施工在同类工程中的实施、推广提供有益的借鉴。 Based on the construction of the main span of the Mazeras super major bridge with(40+64+40)m, the process of the cantilevered casting and the measurements, which includes the key controlling content of the construction of 0#block, the movable suspended scaffolding, the pretressing, the construction of closure segment and linear adjustment in cantilevered process are briefly presented in this paper. The key controlling points and the measures mentioned above ensure the construction progress and quality of the cantilever construction, as well as the final alignment and internal force of the bridge all meet the design requirements,which provide some useful reference for the implementation and promotion of such cantilever casting construction in similar projects
作者 韩龙 韩金秀
出处 《工程建设与设计》 2016年第12X期140-141,147,共3页 Construction & Design for Engineering
关键词 悬臂浇筑 挂篮 预应力钢束 合龙 线形控制 cantilevered casting movable suspended scaffolding prestressed steel closing segment linear control
  • 相关文献

参考文献2

二级参考文献7

  • 1薛吉岗.客专铁路施工质量验收标准应用指南[M].北京:中国铁道出版社,2005:757-758.
  • 2叶澄中.建设工程施工安全技术操作规程[M].北京:中国建筑工业出版社,2004:21-22.
  • 3赵国堂,李化建.高速铁路高性能混凝土应用管理技术[M].北京:中国铁道出版社,2008:191-192.
  • 4中铁九局集团.TB10301--2009铁路工程基本作业安全技术规程[S].北京:中国铁道出版社,2009.
  • 5铁道第三勘察设计院.铁建设[2007]47号新建时速300~350公里客运专线铁路设计暂行规定[s].北京:中国铁道出版社,2007:52-59.
  • 6中铁工程设计咨询集团有限公司.TB10002.3-2009铁路桥涵钢筋混凝土和预应力混凝土结构设计规范[s].北京:中国铁道出版社,2009:91.92.
  • 7姜伟.大跨度连续梁施工和线型控制技术[J].铁道建筑,2010,50(1):92-94. 被引量:17

共引文献32

同被引文献4

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部