摘要
若羌河水库工程区地势狭窄,两岸岸坡陡峭,施工交通布置较为困难,通过对水工建筑物施工期运输要求分析,采用道路、交通洞、桥梁相互结合布置,能够很好的实现该工程施工交通设计,并服务于工程现场。
The engineering area of Ruoqianghe reservoir is very narrow,the bank slope is steep and the construction is difficult.Through the analysis of transportation requirements during the construction period,the road,traffic hole and bridge are arranged in combination with each other,and the construction traffic design can be realized well,and it can serve the project site.
作者
李泽鑫
LI Zexin(Xinjiang water Conservancy and Hydropower Survey and Design Institute,Urumqi 830000,China)
出处
《广东水利水电》
2019年第3期76-78,共3页
Guangdong Water Resources and Hydropower
关键词
施工交通设计
道路
交通洞
桥梁
construction traffic design
road
traffic hole
bridge