梅州某变电站水土流失分析、施工监测及防治研究

Soil and Water Loss Situation Analysis,Construction Monitoring and the Prevention Research on Substation in Meizhou
下载PDF
导出
摘要 嘉应变电站工程是粤东北地区的一座枢纽变电站,工程动工后水土流失情况严重,文中对其水土流失的影响因素、水土流失特点及土壤侵蚀模数等现状进行详细的调查研究。为了及时掌握变电站主体工程水土流失动态,必须对其进行长期监测,并针对当地降雨量大、降雨历时长、侵蚀能力较强、潜在水土流失危险性大等特点,制定了监测方案,提出了防治建议。 Jia Ying transformer substation project is a hub in northeast Guangdong,and the soil and water loss situation is very serious after the project starts. The affecting factors,characteristics and soil erosion modulus of Jia Ying transformer substation project are investigated and researched on the detailed. In order to grasp the dynamic of the soil and water loss situation in time,must carry on the long-term monitoring,the monitoring principle and monitoring content is determined. Finally based on large rainfall,rainfall duration long,strong ability to erosion and great potential risk of soil erosion of Jia Ying transformer substation,this paper develop a monitoring scheme,and put forward the prevention and cure suggestions.
作者 刘春尚
出处 《广东土木与建筑》 2014年第7期54-55,50,共3页 Guangdong Architecture Civil Engineering
关键词 变电站 水土流失 监测 土壤侵蚀模数 transformer substation soil and water loss monitoring soil erosion modulus
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部