摘要
以深圳市某污水处理厂尾水工程工作井施工为研究对象,提出工作井施工采用"沉井法结合逆作法"的施工技术,重点介绍了工艺转换的原因、利弊分析以及方案的设计施工要点。
The purpose of this study is to present the working well construction technology using the Open caisson method Combined Reverse method,in application of tail water project of a sewage treatment factory. Especially,we analyzed the reasons of the conversion process,the pros and cons and design elements.
出处
《广东土木与建筑》
2015年第7期56-58,共3页
Guangdong Architecture Civil Engineering
关键词
抛石填海区
工作井
逆作法
沉井法
riprap reclamation
working well
reverse method
open caisson method