摘要
双圈环绕无粘结预应力锚索技术是当前世界在隧洞施工中最先进的技术 ,成功地解决了薄覆盖层的地下洞室群密集分布与高水头对洞室承压要求的矛盾 ,最大限度地缩小了开挖洞径 ,减少了洞身衬砌的钢筋安装量与混凝土浇筑量 ,降低了成本。
The double ring and non bonding pre stress tendon technique is the art of state technology in tunnel construction in the world. It successfully tackles the contradiction of densely distributed tunnels with thin overburden and requirement of high head on tunnel bearing capacity, minimizes the excavated tunnel diameter, reduces the field reinforcement and concrete volume placed for tunnel lining and thus the costs. The paper presents the methods adopted for the relevant procedures of the tunnel's non bonding pre stressed concrete construction.
出处
《西北水电》
2002年第4期27-29,共3页
Northwest Hydropower