摘要
文章介绍了山西“引黄入晋”工程南干线4~7号隧洞衬砌施工中预制混凝土管片的生产、安装的有关情况及其对工程质量的影响,并对管片的生产和安装工艺提出了建议。
The paper introduces the production and installation accuracy of precast concrete segments, which are used for the lining of No. 4 - No. 7 tunnels of South Trunk of Shanxi Yellow River Diversion Project, and presents some suggestions on the production and installation of segments.
出处
《现代隧道技术》
EI
2002年第6期38-41,共4页
Modern Tunnelling Technology