摘要
文章通过对连拱隧道先中导洞开挖、中隔墙混凝土灌注、中隔墙顶部混凝土回填、中隔墙防偏压处理等方面的介绍,总结了双跨连拱隧道先中隔墙施工后正洞掘进的一些经验。
In this paper, some experience on CRD method prior to main tunnel excavation are summarized, which is characterized by the sequence of medium pilot excavation, concrete pouring, top back -filling and the countermeasures against bias pressure during the construction of tunnel with double continuous spans.
出处
《现代隧道技术》
EI
2001年第6期44-47,共4页
Modern Tunnelling Technology
关键词
双跨连拱隧道
中隔墙
施工方案
中导洞
Tunnel with Double Continuous Spans
CRD Method Construction