摘要
介绍运行机组主给水调节阀更换后的调试试验项目,分析了调试试验风险并提出了应对措施。着重介绍主给水调节阀调试过程中出现的问题及处理方法。
This essay introduces commissioning tests after replacement of main feed water control valve of operating unit, analyzes risks of commissioning tests and provides counter-measures. It also mainly stresses problems emerged from commissioning tests of main feed water control valve as well as their treatment.
出处
《核动力工程》
EI
CAS
CSCD
北大核心
2015年第S1期114-117,共4页
Nuclear Power Engineering
关键词
主给水调节阀
超调
振荡
定位器
放大器
摩擦
Main feed water control valve,Overshooting,Oscillation,Positioner,Booster,Friction