本文针对110k V和35k V变电站,在雨季期间发生接地事故时,电力调度室调度员进行事故处理的思路和方法,并对造成故障的基本原因进行了分析和总结。
This paper is mainly based on 110 k V and 35 k V substations, when the ground faults are occurred in therainy season, the faults management ideas and methods of power control center dispatcher, and the basic reason caus-ing the fault of were analyzed and summarized.
出处
《河南科技》
2015年第06X期134-135,共2页
Henan Science and Technology
关键词
电网
雨季期间
接地
事故处理
power network,the rainy season,grounding