摘要
待拆四联体钢筋混凝土结构筒仓群,高宽比接近1。爆破前通过对筒仓群进行预切缝,使其成为相对独立结构;采用秒差多段延期爆破方案,使两两独立的筒仓分别向南、北方向倒塌。文中论述了爆破设计方案、爆破参数和切口高度的确定以及起爆网路的设计与施工等。
The four interconnected reinforced concrete silos to be demolished have relatively small ratio of heighttowidthBefore blasting,the silos were cut and divided into two separate structuresBy use of seconddelay blasting,the two separate structures were made to collapse to the south and north respectivelyIn the paper,the design of blasting scheme,the determination of blasting parameters and cut height,blasthole pattern and blasting network were discussed
出处
《工程爆破》
2002年第4期29-31,46,共4页
Engineering Blasting