期刊文献+

京津唐电网进一步开发抽水蓄能电站的时序分析

Analysis on time arrangement of developing pumped storage power station for Jing-jin-tang Power Grid
下载PDF
导出
摘要 京津唐电网为火主电网 ,电网电源结构单一 ,随着电网负荷及负荷峰谷差的增加 ,调峰容量严重不足。为满足电网调峰需求及改善电网电源结构 ,需建设一定容量的抽水蓄能电站。为此 ,就距负荷中心较近、开展工作较多的丰宁、板桥峪、桃花寺三座抽水蓄能电站进行比较分析 ,提出一较为合理。 The Jing jin tang Power Grid is a thermal power dominated system with the simple power source structure. With the increase of load of the Grid and the load difference between peak and valley load, the system will be seriously lack of peaking capacity. To meet the peaking need of the Grid and improve the source structure of the system, the pumped storage power station with a certain capacity will be needed. This article, on basis of analysis and comparison with the Fengning, Banqiaoyu and Taohuasi pumped storage stations, presents a reasonable and feasible scheme of time arrangement as well as give some advices of further development for reference.
作者 钟进
出处 《水力发电》 北大核心 2003年第1期4-7,共4页 Water Power
关键词 京津唐电网 抽水蓄能电站 时序分析 电网 调峰 备用容量 pumped storage power station,development time arrangement, peaking demand of power grid,reserve capacity,comparison between projects, Jing jin tang Power Grid
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部