摘要
介绍了襄樊电厂 4号机组 2号高速混床 ( 4 5 6m3 /h)损坏的情况 ,分析了产生的原因 。
The paper introduces the damage situation of the NO.2 high speed mixed bed of NO.4 turbine unit in Xiangfan power plant, analyses its cause, and puts forward material disposal scheme and suggestions.
出处
《湖北电力》
2003年第1期44-45,共2页
Hubei Electric Power