期刊文献+

灯泡机组径流水电站全枢纽过渡过程计算研究 被引量:1

The bulb turbine's transient calculation and research of the all hinge of riverbed power station
下载PDF
导出
摘要 在与灌溉相结合的灯泡式机组径流水电站系统中 ,其稳态初值的计算和全枢纽过渡过程的计算都是难点 ,而且由于径流式水电站的特殊性 ,有时需要考虑河床涌浪的影响。针对带有灌溉系统并装设灯泡式机组的径流水电站 ,进行了计及涌浪影响的全枢纽过渡过程计算 ,并在稳态初值计算中使用虚拟阻抗法对流体网络进行求解 ;计算及分析了涌浪对枢纽机组过渡过程的影响及由涌浪引起的对枢纽运行机组的水力干扰情况。计算结果表明 ,坝前。 In the bulb turbine of the riverbed power station system in combination with irrigation system, it's difficult to calculate the initial value and the transient, and for the particularity of the riverbed power station, sometimes the effect of the ground swell need to be taken into account. For this reason, this paper puts forward the method of virtual resistance to calculate the initial value of this system and to calculate the transient considering the effect of the ground swell. Meanwhile, this paper also researches the effect of the ground swell on the transient and the running bulb turbine. The results showed that the ground swell 's effect is evident on the transient.
机构地区 清华大学
出处 《水力发电》 北大核心 2003年第2期45-48,共4页 Water Power
关键词 径流水电站 灯泡式水轮机 明渠 过渡过程 特征线法 bulb turbine, open channel, transient, Characteristic Lines
  • 相关文献

参考文献1

二级参考文献5

  • 1麦赫默德 林秉南译.明渠不恒定流[M].北京:水利电力出版社,1987..
  • 2刘立宪 李辉 等.大型输水或发电工程动态仿真中明流管流联合计算问题研究[M].全国水利水电水力机械信息网1997年会,1997,10..
  • 3Lin Xiaohan,XIXIAHR Sympo,1998年
  • 4刘立宪,全国水利水电水力机械信息网1997年会,1997年
  • 5麦赫默德,明渠不恒定流,1987年

共引文献19

引证文献1

二级引证文献1