针对胜利发电厂循环冷却水中泥沙、悬浮物含量高的问题 ,在冷却塔水池内建成一平流式絮凝沉淀池。沉淀池运行后 ,循环冷却水浊度下降 6 8%左右 ,水质改善明显 。
In view of the problems concerning high content of silt and suspended matters in circulatory cooling water in Shengli Power Plant, a horizontal flocculation and sadimendation basin has been constructed in the water-pool of cooling tower, After putting the said basin into operation, the turbity of circulatory cooling water has been lowered about 68%, the water quality obviously improved, so that the level of safe and economic operation of the unit can be enhanced.
出处
《热力发电》
CAS
北大核心
2003年第2期58-59,共2页
Thermal Power Generation